As the U.S. population grows, so too does demand for energy. This demand has fueled a steady increase in coal production, as coal-fired power plants are one of the most inexpensive ways to produce electricity in the United States. Since 1978, U.S. coal production has increased from 417 million tons to 1,082 million tons in 2002. This increase is expected to continue for the foreseeable future.
After coal is burned at the plant, the residual ash is removed from the boiler and sent to a holding area. The ash can contain metals like arsenic, vanadium or mercury, so it must pass a TCLP (Toxicity Characteristic Leaching Procedure) test to determine if the amount of metals leaching from the pile pose a threat to the surrounding water table. This test measures the amount of metals that would leach from a material if it were exposed to acid rain. If the ash passes the test, it can be used as a fill material for mine reclamation or some other purpose.
As these piles accumulate at a plant, the runoff is typically collected and tested for metals prior to discharge. As testing methods improve and more is learned about harmful effects of some metals, discharge standards are reduced. When the retention pond contains metals exceeding discharge standards, the runoff must be treated or hauled off site for disposal.
Assessing Options
When a coal-fired power plant in the Northeast discovered that the runoff from its ash pile contained vanadium levels exceeding discharge limits, it contacted a water treatment vendor for assistance.
The plant’s small retention pond contained roughly 400,000 gallons of water with 30 ppm of vanadium. Operators asked the water treatment vendor for a temporary solution that would remove the vanadium to less than 4 ppm. Based on results of a water analysis performed by the vendor (see Table 1), several technologies were considered. Trailer-mounted reverse osmosis (RO), chemical treatment, ion exchange or simply hauling the water offsite for treatment were evaluated as possible solutions.
Reverse Osmosis
According to a computer model supplied by an RO membrane manufacturer, this process could remove the vanadium. As the installation site had no existing structures to protect the RO from the elements, a trailer-mounted RO system seemed to be the best solution. It could be delivered quickly and would be completely enclosed. Plant personnel ruled out the RO system, however, because of the additional waste streams it would produce (i.e., concentrated permeate) and manpower required to support the unit.
Ion Exchange
Test results showed ion exchange (IX) resin would remove roughly two pounds of metal for every cubic foot of resin. Calculations indicated the entire pond could be treated with less than 60 cubic feet of media.