Optimizing offshore pump performance and reliability

Oct. 20, 2020
Assessing the benefits of pump retrofit projects that deliver improvements and savings

Asset reliability and performance are the two most important factors for the oil and gas sector, but as processes change and equipment ages, optimizing uptime can become a greater challenge. For pumping assets, a retrofit project has the potential to increase productivity and reliability, while at the same time reducing energy costs.

Changes to pump performance may be required for several reasons. For instance, refineries looking to increase production will examine the assets involved and identify any bottlenecks. In some cases flowrates will need to be increased beyond the existing capabilities of the equipment; a drilling well may need to increase water injection rates, or the reliability of certain assets may need to be improved to meet the new targets.

New for Old

The first, and most straightforward, solution is to replace the existing pumps with new equipment that has been specified for the new production rates. This has many advantages in terms of reliability, performance and efficiency; using the latest materials and design technology will ensure a long-lasting and effective solution.

There are, however, some drawbacks — the time to complete the project, the lost production while the work is completed and the overall capital expenditure. Together, these will nearly always rule this option out.

Adapt and Survive

A more favorable option is to modify the existing assets to enable them to deliver the new targets. There are many challenges that can be resolved to some degree by implementing a retrofit project. Reliability issues can be improved through a change in materials to resolve erosion or corrosion; performance can be enhanced by altering the hydraulic design of the pump.

Retrofit projects are a cost-effective alternative to replacing large assets when a production site requires a change in performance or an improvement in reliability. By minimizing the number of components being modified, both the time and the cost involved in the project are kept to a minimum.

For example, in Norway, the government offers support to the oil and gas industry to reduce its carbon footprint. One of the biggest gains can be achieved by reducing the energy consumption of pumping assets. Using a retrofit project to optimize pump performance to each application, operators have made significant savings in running costs, which help to meet national carbon targets.

Optimized Performance

One of the major areas of pump operation is water injection systems, which are used to maximize the productivity of the oil wells. As the oil field matures, there is a need to increase the water injection rates to maximize oil production. This requires the capacity of the injection pumps to be increased without affecting the layout of the plant or the existing pipework.

In this case, the flowrate needs to increase while maintaining the head, which means that the power demand will rise, and the pump design will need to be altered. By working closely with the platform engineers and establishing the limits of the motor or turbine, pump designers can draw up a modified hydraulic proposal that will improve both performance and efficiency.

In an alternative scenario, the system pressure may need to be reduced, while maintaining the original flowrate. Reducing the pressure generated by a pump can be achieved by removing several stages from the pump rotor, which will significantly decrease the energy requirement of the pump. In some cases, the rerate solution may include a variable speed drive, which can deliver more flexibility in the output from the pump.

Rerating a pump’s hydraulic conditions to the new duty point, a combination of flow and head, will enable the system to operate more efficiently. Based on the downstream requirements, the pump characteristics can be redesigned so that it delivers the necessary flow and pressure while operating at or close to its best efficiency point (BEP).

Case in Point

One of the largest offshore oil fields in the Middle East uses five BB5 injection pumps, four 9 MW Weir pumps and a 14 MW Sulzer HPcp pump, all of which are powered by gas turbines. The proposal was to increase production from the oil field, which would require the gas turbines to be upgraded to provide their maximum achievable power output. Having achieved this, all five pumps would be rerated to deliver the maximum possible injection flow rates using the increased power capacity.

As both a pump original equipment manufacturer (OEM) and an independent maintenance provider, Sulzer was awarded the contract to upgrade all five pumps. The objective was to achieve the best possible flow rates using as many existing components as possible, and with minimal disruption to the production schedule,

Sulzer had access to a complete, spare cartridge for the Weir pumps, from which all the necessary design information could be gathered and used as a base to modify the cartridge design. The proposal was to change the original 4-stage design for a 3-stage alternative with a similar diameter impeller. This allowed the existing pipework, lube systems, mechanical seals, bearing housings and site interfaces to be retained.

Increasing Productivity

Using the spare cartridge, Sulzer implemented the new barrel design and delivered it back to the platform where it took the place of one of the operational pumps. The whole process to remove and install the new barrel only took three days to complete, including commissioning. The original cartridge that had been removed was taken back to Sulzer’s engineering center where it underwent the same design rerate process.

Following this implementation plan ensured that operations on the platform were unaffected by the rerate project, eliminating any lost production costs and minimizing the amount of work that needed to be completed on the platform. The upgraded cartridges delivered a 25% increase in flow over the original design of the four pumps, with the total injection capacity rising by 30%.

When compared to a project to procure new pumping equipment to do the same task, the rerate program not only saved the platform operator a total of $150 million, but it avoided all of the disruption that a new installation would create.

About Sulzer

Sulzer is a global leader in fluid engineering. They specialize in pumping, agitation, mixing, separation and application technologies for fluids of all types. www.sulzer.com

Sponsored Recommendations

Meet the future of MV switchgear

SureSeT new-generation metal-clad. Smarter. Smaller. Stronger.

A digital circuit breaker built for the future

EvoPacT medium voltage digital vacuum circuit breaker

The New Generation of Intelligent MV Switchgear

Step into the future of electrical infrastructure with Intelligent MV Switchgear - where traditional equipment becomes smart, providing real-time data on critical components like...

Switchgear goes digital with SureSeT

Discover what you can do with Square D natively digital MV metal-clad switchgear.

Request More Information

By clicking above, I acknowledge and agree to Endeavor Business Media’s Terms of Service and to Endeavor Business Media's use of my contact information to communicate with me about offerings by Endeavor, its brands, affiliates and/or third-party partners, consistent with Endeavor's Privacy Policy. In addition, I understand that my personal information will be shared with any sponsor(s) of the resource, so they can contact me directly about their products or services. Please refer to the privacy policies of such sponsor(s) for more details on how your information will be used by them. You may unsubscribe at any time.