Detecting and reducing boiler scale buildup in a pharmaceutical plant

Jan. 17, 2019

This case study describes how a water technologist and plant engineer collaborate to manage calcium carbonate scale in a boiler system.

One of the most prominent issues experienced with boilers is the formation of calcium carbonate scale on boiler tubes due to improper calcium levels within the feedwater system supplying the boiler. If left untreated, this scale — even if only a couple millimeters thick — can cause uneven heating and increased operational costs and potentially result in premature boiler failure. Often, improper calcium levels occur when a feedwater softener is not functioning properly, but what if calcium issues are observed on a system with a properly working softener? 

Figure 1. Solids collected from a boiler during initial remediation. All figures courtesy of U.S. Water

After working with its water treatment vendor for three years, a Southern U.S. pharmaceutical plant found all three of its on-site boilers scaled. The plant leaned on the current vendor’s abilities to identify and diagnose the issues. Based on the monthly water analysis reports, the plant’s treatment program seemed to be operating satisfactorily. Therefore, plant engineers were understandably confused and frustrated after an open boiler inspection revealed extensive scale formation in all three boilers. The boiler scale and a low return rate were causing increased fuel and operational costs, causing the plant to seek a second opinion.

A U.S. Water representative conducted a plant survey in an attempt to uncover the boiler system issue. At first glance, everything looked relatively normal. Surface blowdown controllers located on all three boiler systems had setpoints within range to run efficiently, and the water treatment vendor at the time was using a solid phosphate/caustic/amine/sulfite chemical program. After reviewing the gauges and sensors on the deaerator and feedwater equipment, the representative inspected the deaerator tank and discovered the water temperature was at 170oF, and the pressure was 5 psi. Deaerator tanks are meant to operate within 3°F of saturation to mechanically reduce dissolved oxygen as low as possible. At 5 psi, the boiling point of water is increased to 227°F, so one would expect to see at least 220°F. Plant engineers had mentioned they had noticed a steady decline in the temperature over the last year.

Figure 2. Prior to treatment, boiler tubes showed heavy calcium carbonate scale formation.

Troubleshooting feedwater softener system

It is common on newer softener systems to see lower calcium levels in the feedwater downstream of the softener due to improper regeneration settings during setup. On older units, it may be due to a loss of resin capacity.  Keeping in mind the formula for feedwater (makeup+condensate return), this system did not fall into one of those categories. Starting with the basic foundations of proper system operation, the representative used a process of elimination to identify the root cause of the issue. The feedwater softener operation was verified with conductivity and hardness testing and was performing as designed with no hardness present and conductivity of 238 microSiemens per cubic centimeter (µS/cm3). The representative moved to the condensate tank located at the farthest point on the steam system from the deaerator and ran the same two tests that were performed on the water softeners and deaerators. 

The results from the condensate tank revealed a conductivity of 250 µS/cm3 and a calcium hardness of 38 parts per million (ppm). Conventionally, anything over zero calcium hardness in feedwater indicates an issue with the system that needs to be addressed.  

Properly maintaining heat exchangers

It is critical to check condensate return portions of heat exchangers, as they typically operate as gravity feed systems back to condensate return tanks with little pressure in the lines. City water supply pressures at this location were 40 psi, so the natural tendency for water to take the path of least resistance will cause an unwanted hardness intrusion back into the condensate return supply. All heat exchangers on-site that were connected to the steam distribution system were also reviewed, allowing the U.S. Water representative and plant engineer to zero in on the hot water distribution system that provided heating for the reheats on the HVAC system. The hot water distribution was heated from a shell and tube heat exchanger tied into the steam distribution system. A pressure gauge on the hot water side of the system indicated the hot water loop was 10 psi lower than optimal operating pressure. 

Pressures on closed systems are controlled primarily with the makeup water line and pressure regulator, which prompted the team to review the makeup water bypass where they discovered the valve slightly open. A calcium hardness test performed on the condensate return from the heat exchanger revealed calcium levels almost identical to the city water in the area at 40 ppm, but best practice on a properly working pharmaceutical plant should be 0 ppm calcium. This was a clear indication that the closed-loop system was losing water, being consistently replaced with city feedwater, and sending large amounts of hardness to the boiler system. The representative identified the root cause behind the system’s scale and low condensate return rate.

U.S. Water’s team partnered with plant engineers to develop and implement a remediation and maintenance plan to mitigate the issue. Unfortunately, the effects of corrosion cannot be undone. However, by implementing the proper treatment plan, plants can prevent continued damage and secure the remaining life span of the equipment. In an industry such as pharmaceuticals, disruption of production is extremely costly and has far-reaching implications. Heat exchangers are costly to service and replace, and repairs can take months due to long lead items. When calcium levels are more than 5 ppm, using a chemical solution to control scale is not a feasible or cost-effective approach. 

Figure 3. The boiler tubes after one year of recommended remediation and maintenance plan.

Solution

U.S. Water developed a solution to meet the pharmaceutical plant’s operational needs. The contaminated condensate was rerouted from the condensate return to the nearest all-metal drain line, while system repairs were made.  Boiler setpoints were reduced to increase the rate of solids removal and encourage increased soft water makeup into the boiler system until all traces of hardness were no longer entering the boiler feedwater system. Recommendations were also made to increase the bottom blowdowns to four to six times per day to prevent sludge formation from hardening and clogging the blowdown lines. The chemical phosphate program was then adjusted to a chelant chemical program to remove existing scale and reduce the system’s salt consumption. 

The program was enhanced with a proactive digital solution. U.S. Water’s automation package was introduced for both cooling tower systems, along with boiler blowdown controllers for online monitoring. The control technology featured several inputs to allow engineers to monitor boiler and deaerator conductivity and send instant alarms directly to the facility engineer and U.S. Water if either were outside the desired level. Once coupled with the daily dashboard, the plant engineer received daily system summaries, allowing for complete transparency of the water treatment program. 

Figure 4. The plant experienced approximately $25,000 in fuel savings one year after implementation.

Conclusion

After implementing the solution, the customer noticed energy savings and improved system efficiency. Both of the cooling tower systems’ corrosion coupon results started trending down to acceptable levels, and condensate return water quality contained zero hardness. The level of condensate return was steady around 80 percent, a dramatic increase from less than 28 percent. 

If a boiler system issue arises, a proactive approach of effective diagnostics and remediation using advanced technologies can ensure the facility is protected. A partnership between facility engineers and water treatment professionals can positively affect facility operations in terms of equipment reliability, system downtime and operational cost.  

Justin Treece, with U.S. Water Services Inc., has more than 10 years of experience in industrial, health care and commercial water treatment services, focusing on enhancing system reliability, efficiency and profitability. He has a Bachelor of Arts in Economics from Wofford College in Spartanburg, South Carolina.

Ray Gesling has more than 10 years of process and operational engineer experience in a variety of industries. He has a Bachelor of Science in Mechanical Engineering from the University of Central Florida.

Sponsored Recommendations

Meet the future of MV switchgear

SureSeT new-generation metal-clad. Smarter. Smaller. Stronger.

A digital circuit breaker built for the future

EvoPacT medium voltage digital vacuum circuit breaker

The New Generation of Intelligent MV Switchgear

Step into the future of electrical infrastructure with Intelligent MV Switchgear - where traditional equipment becomes smart, providing real-time data on critical components like...

Switchgear goes digital with SureSeT

Discover what you can do with Square D natively digital MV metal-clad switchgear.