Alberta proposes new restrictions on data centers

Alberta’s proposed Bill 42 would set minimum distances from homes, protect high-quality and irrigated farmland, and tighten water and environmental rules for large data centers.

Key Highlights

  • Bill 42 would require data centers of 10 megawatts or more to be at least 600 m from the nearest home.
  • The proposal would protect about 14 million acres of high-quality farmland and prohibit large data centers on irrigated land.
  • New standards would aim to bring data center cooling-water use near zero and require designs that enable excess-heat recovery.

The government of Alberta has proposed new restrictions on data centers to protect communities, farmland, water, and electricity while ensuring responsible growth.

These restrictions came from feedback from Albertans and build on existing rules. If passed, Bill 42, the Energy, Environment, and Utilities Statutes Amendment Act, 2026, will establish minimum distances between data centers and homes, known as setbacks, and introduce stricter standards for data center development, including for water use and farmland protection.

If passed, amendments and supporting regulations would restrict data centers that are 10 megawatts or larger from being built within 600 m of the nearest home or on Alberta’s highest-quality farmland, protecting about 14 million acres of Class 1 and 2 agricultural land, as well as Class 3 land in municipalities without Class 1 or 2 land.

Large data centers would also be prohibited on irrigated land. In certain circumstances, alternative setbacks could be set by municipalities where local planning supports compatible development. Existing noise requirements would continue to apply.

Changes would also support the development of a provincewide water use standard to bring data centers cooling water usage to near zero, while requiring that data centers be designed and operated for excess heat recovery for greenhouses, industry, or homes.

To address pollution concerns, amendments would increase maximum fines for corporations, including data center operators, to $6 million for serious environmental contamination, in addition to existing cleanup and remediation obligations.

The proposed changes would also advance the Mature Asset Strategy, reduce regulatory duplication, and strengthen environmental enforcement and penalties for illegal dumping, as well as targeted utility affordability initiatives.